January 30, 2007 08:16 ET

Denison Announces Operations Update

TORONTO, ONTARIO--(CCNMatthews - Jan. 30, 2007) - Denison Mines Corp. ("Denison" or the "Company") (TSX:DML) is pleased to announce that it has awarded E.D. Mining, LLC, the contract to conduct contract mining at the Company's Sunday mine in the United States. Mining has commenced and production from the Sunday mine is expected to add about 100 tons of ore daily to the current daily U.S production from the Pandora, Topaz and St. Jude mines that will aggregate to about 550 tons per day by mid-2007. Production from these mines, in the area known as the Colorado Plateau District, is being hauled to Denison's White Mesa Mill and is currently being stockpiled. Milling of conventional ore is scheduled for early 2008 when the milling of the alternate feed is completed and at least 150,000 tons of ore is stockpiled at the Mill.

The Company will be evaluating the Rim and Van 4 mines on the Colorado Plateau with the plan to commence operations in 2007.

At the Tony M mine within the Henry Mountains Complex, which is located west of the Colorado Plateau District, permitting is progressing well and it is expected that full operational permits will be received by the end of the first quarter, 2007. Rehabilitation of the mine will commence within the next few months under the exploration permit that the Company has in place for the Tony M mine. Production from this mine is anticipated in the third quarter of this year.

At the White Mesa Mill, the Company has implemented a US $15 million modernization program which will include modifications to the mill circuit, upgrading of equipment and relining of tailings cell 4A. The Mill continues to process alternate feed material from several large contracts. Production at the White Mesa mill in 2006 was approximately 280,000 pounds of U3O8 and it is anticipated that production in 2007 will be about 400,000 pounds. By 2010, production levels from U.S. operations are anticipated to reach greater than 3 million pounds U3O8 and 4.5 million pounds of vanadium. The Company intends to maximize the advantage of its ownership of one of only two operating mills in the U.S. To that end, in addition to processing its own ore and alternate feed material, the Company is negotiating toll milling arrangements with other mines in the region.

In Canada, mining at the Sue E pit at McClean Lake in northern Saskatchewan is proceeding on schedule with a scheduled completion by the end of this year. U3O8 production at the McClean Lake mill, in which Denison has a 22.5% interest, was 1,795,000 pounds in 2006 (Denison's share was 404,000) and it is anticipated that the joint venture production in 2007 will be 2.2 million to 3 million pounds. The large variance in this estimate is a result of the uncertainty associated with the drilling of the bore holes for the jet boring mining at the McClean North deposit, the completion of mill modifications to increase the leaching capacity at the mill and the time required to obtain regulatory approvals to implement the mill modifications. Production levels at McClean should continue to increase and by 2011, with Midwest ore production and another mill expansion, production should be about 9 million pounds per year.

Denison Mines Corp. is the premier intermediate uranium producer in North America, with mining assets in the Athabasca Basin Region of Saskatchewan, Canada and the southwest United States including Colorado, Utah, and Arizona. Further, the Company has ownership interests in two of the four uranium mills operating in North America today. The combination of a diversified mining asset base with parallel ownership of milling infrastructure in highly politically stable jurisdictions has uniquely positioned the Company for growth and development into the future. The Company also has a strong exploration portfolio with large land positions in the United States, Canada and Mongolia. Correspondingly, the Company has one of the largest uranium exploration teams among intermediate uranium companies.

Cautionary Statements

This news release contains "forward-looking statements", within the meaning of the United States Private Securities Litigation Reform Act of 1995 and similar Canadian legislation, concerning the business, operations and financial performance and condition of Denison Mines Corp. ("Denison").

Forward-looking statements include, but are not limited to, statements with respect to estimated production, synergies and financial impact of the proposed transaction; the benefits of the proposed transaction and the development potential of Denison's properties; the future price of uranium; the estimation of mineral reserves and resources; the realization of mineral reserve estimates; the timing and amount of estimated future production; costs of production; capital expenditures; success of exploration activities; permitting time lines and permitting, mining or processing issues; currency exchange rate fluctuations; government regulation of mining operations; environmental risks; unanticipated reclamation expenses; title disputes or claims; and limitations on insurance coverage. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved".

Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Denison to be materially different from those expressed or implied by such forward-looking statements, including but not limited to risks related to: unexpected events during construction, expansion and start-up; variations in ore grade, tonnes mined, crushed or milled; delay or failure to receive board or government approvals; timing and availability of external financing on acceptable terms; risks related to international operations; actual results of current exploration activities; actual results of current reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of uranium and vanadium; possible variations in ore reserves, grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays in the completion of development or construction activities, as well as those factors discussed in or referred to in the current annual Management's Discussion and Analysis of each of Denison Mines Inc. ("DMI") and International Uranium Corporation ("IUC"), the current Annual Information Form of DMI filed with the securities regulatory authorities in Canada and available at www.sedar.com and IUC's Annual Report on Form 20-F filed with the securities regulatory authorities in Canada and available at www.sedar.com. Although management of Denison has attempted to identify important factors that could cause actual results to differ materially from
those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended.

There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Denison does not undertake to update any forward-looking statements that are incorporated by reference herein, except in accordance with applicable securities laws. Mineral resources, which are not mineral reserves, do not have demonstrated economic viability. Readers should refer to the respective Annual Information Forms of DMI and, IUC, each for the year ended December 31, 2005, and other continuous disclosure documents filed by each of them since January 1, 2006 available at www.sedar.com, for further information relating to their mineral resources and mineral reserves.

Cautionary Note to United States Investors Concerning Estimates of Measured, Indicated and Inferred Resources: This news release uses the terms "Measured", "Indicated" and "Inferred" Resources. United States investors are advised that while such terms are recognized and required by Canadian regulations, the United States Securities and Exchange Commission does not recognize them. "Inferred Mineral Resources" have a great amount of uncertainty as to their existence, and as to their economic and legal feasibility. It cannot be assumed that all or any part of an Inferred Mineral Resource will ever be upgraded to a higher category. Under Canadian rules, estimates of Inferred Mineral Resources may not form the basis of feasibility or other economic studies. United States investors are cautioned not to assume that all or any part of Measured or Indicated Mineral Resources will ever be converted into Mineral Reserves. United States investors are also cautioned not to assume that all or any part of an Inferred Mineral Resource exists, or is economically or legally mineable.

Contact Information

  • Denison Mines Corp.
    E. Peter Farmer
    (416) 979-1991 ext. 231
    or
    Denison Mines Corp.
    Ron Hochstein
    (604) 689-7842
    or
    Denison Mines Corp.
    James Anderson
    (416) 979-1991 ext. 372
    (416) 979-5893 (FAX)
    Website: www.denisonmines.com