Petaquilla Minerals Ltd.: Molejon Gold Project Update

Production Scheduled to Commence in July 2007

VANCOUVER, BRITISH COLUMBIA--(CCNMatthews - Jan. 17, 2007) - Petaquilla Minerals Ltd. ("Petaquilla" or the "Company") (TSX:PTQ)(OTCBB:PTQMF)(FWB:P7Z) is pleased to provide an update on the ongoing activities at its 100%-owned Molejon Gold Project in Panama. The progress made at the project has reaffirmed management's original schedule of performing the first gold pour in July 2007. As outlined in the technical report completed by SRK Consulting in October 2005, the Company expects production at Molejon to be 120,000 ounces of gold annually with an estimated cash cost of US$165 per ounce. Estimated capital costs are US$34 million, and the plant will have a projected capacity of 2200 tons per day.

Under the coordination of Sococo, the official contract miner, and TechProMin (Chile), the project engineering firm, the Company has made significant progress in its construction and procurement plan. Three ball mills have arrived in Panama and are presently at the Company's staging area adjacent to the Company's offices at La Pintada. It is anticipated that they will be delivered to the project site by the middle of February. Four diesel generators that will provide electrical power sufficient to run Molejon's operations are also expected to arrive shortly. The majority of the other major components have now been ordered and have firm quotations and delivery times associated with them.

The Company has entered into a US$15.8 million equipment lease purchase finance facility which, when combined with the proceeds of the equity issue of $17.56 million raised in October 2006, results in the project being fully funded.

The Company also announced that the ongoing resource and, if applicable, reserve re-classification being compiled by SRK is close to completion and the results will be released immediately upon receipt by the Company.

Important progress on road construction continues on target during the first quarter of 2007. One of the primary objectives is the completion of a 5 km road from Molejon to the Colina Copper camp which at present is 80% complete and has a projected completion date of February 15, 2007. At the same time, the interconnecting road to Botija drill camp is complete, while the Petaquilla drill camp road is under construction. On the Llano Grande-Coclesito Road Improvement Project, the Cascajal Bridge has been completed and was inaugurated January 16, 2007, by the Minister of Public Works of Panama. The 28 km Llano Grande-Coclesito section is being designed to provide both access to the mine site and to comprise part of a future expansion of the national road network connecting communities within the region.

In addition to project production advancement activities, a 40,000 metre exploration and development drill program is presently underway. Six drill crews are currently operating - four from Rodio-Swissboring Company and two from Canchi Perforaciones.

Richard Fifer, CEO of Petaquilla Minerals S.A., said, "We are proud that we have consistently executed the aggressive schedule we adopted at Molejon from the outset of our production decision. Molejon is the first step in our plans for our large holdings in Panama. Our success at Molejon makes us a trailblazer in Panama - a vibrant mining jurisdiction that is now coming to prominence as the next great mineral region in the world."

The Company will be holding a site visit and information tour in Panama from January 22 to 25, 2007. Interested parties wishing to attend are directed to contact Janet Francis at (604) 694-0021.

The statements contained in this news release that are not purely historical are forward-looking statements. Forward-looking statements may relate to the success of any of the Company's strategic initiatives, the Company's expectations, beliefs, growth and future prospects, and the Company's position in the market and future opportunities therein. Forward-looking statements may also include, without limitation, any express or implied statement relating to future events, industry performance, general business and economic conditions or circumstances, regulatory and legal requirements, and other matters, many of which are beyond the control of the Company. Forward-looking statements involve risks and uncertainties, which could cause actual results to differ materially from those projected. All forward-looking statements included in this news release are based upon information available to the Company as of the date hereof and the Company does not undertake any obligations to update forward-looking statements should circumstances or management's beliefs or opinions change.