Anatolia Copler Drilling Indicates Possible New Zone

Copler CRC-573 cuts 41 meters @ 4.1 gpt gold 500 meters west of Main Zone, near previous 23 meters @ 7.2 gpt gold. Nearby holes follow gold mineralization for +300 meters along strike. Elsewhere, CRC-546 cut 62.5 meters @ 2.42 gpt gold and CRC-540 cut 23 meters @ 3.82 gpt gold

TORONTO, ONTARIO--(Marketwire - July 12, 2007) - Anatolia Minerals Development Limited (TSX:ANO) ("Anatolia") is pleased to announce assay results at its 100% owned Copler Gold Project. The drill program was designed to target underlying sulfides in the Main Zone, the area between the Main Zone and Manganese Mine Zone, and other areas adjacent to presently defined reserves and resources. The map attached to this news release is posted to Anatolia's website (www.anatoliaminerals.com).

The current drill program began October 2006. Earlier results were announced previously (see Anatolia News Release, dated March 28, 2007). These latest results include 39 reverse-circulation and 22 diamond core holes aggregating 11,134 meters. There are 5 drill rigs at Copler which are now focusing on in-fill drilling to support the current mine development program.

A summary of Copler drill holes with meaningful results is given below. None of these results were included in the current mine plan or resource estimate for Copler (see Anatolia News Release, dated January 18, 2007 and the Technical Report filed March 2, 2007, both available at www.sedar.com). Given the disseminated nature of the deposit, these intercepts are considered true widths.



Intercept Au
Drill Hole (Meters) Gpt Comments
CDD-122 7 0.8 Oxide: 0-7m
7 2.5 Sulfide: 7-14m
CDD-123 13 0.8 Oxide: 1-13m
23 3.6 Sulfide: 46-53m@5.4gpt Au, 72.5-76m@3.1gpt
Au, 100-104m@3.7gpt Au, 170-178m@2.0gpt Au
CDD-124 16 4.1 Oxide: 0-15.9m@4.1gpt Au, including
0-7m@7.5gpt Au
17 4.2 Sulfide: 27-43.6m@4.2gpt Au, including
28-35.5m@6.3gpt Au
CDD-125 5 1.5 Oxide: 0-5m@1.5gpt Au
CDD-127 10 1.3 Oxide: 89-99m@1.3gpt Au
CDD-129 5 1.2 Oxide: 0-5.1m
22 5.2 Sulfide: 36-48.8m@6.1gpt Au,
127.45-131.2m@4.0gpt Au,
154-159.4m@3.7gpt Au
CDD-130 8 0.7 Oxide: 0-8.25m
20 3.6 Sulfide: 55-63m@3.5gpt Au, 66-69.85m@3.4gpt
Au, 81.2-89m@3.8gpt Au
CDD-131 5 3.3 Oxide: 0-4.7m
12 3.1 Sulfide: 4.7-17m
CDD-133 22 4.1 Sulfide: 21-43m
CDD-134 19 4.6 Sulfide: 66-85m, including 1m@2.2 ounce per
tonne Au (66.5gpt)
CDD-135 9 2.1 Oxide: 0-8.6m
15 4.7 Sulfide: 21.5-36.5m
CDD-137 6 20.1 Sulfide: 55-60.9m
CDD-140 12 4.0 Sulfide: 88-94m@3.6gpt Au, 115-121m@4.5gpt Au
CRD-538 29 2.8 Oxide: 117-146.1m@2.8gpt Au, includes 1m
sulfide
CRC-539 3 3.25 Oxide: 3-6m
CRC-540 12 3.3 Oxide: 141-153m, includes 1.5m cavity
10 4.4 Sulfide: 153-159m@3.1gpt Au, 166-170m@6.4gpt
Au
CRC-543 51 .7 Oxide: 16-67m@.7gpt Au, includes 1m cavity
CRC-546 39 1.9 Oxide: 102-133m@1.0gpt Au, includes 7m
sulfide, 161-168.5m@5.4gpt Au
24 3.2 Sulfide: 137-161m, includes 3m oxide and 1.5m
cavity
CRC-547 14 1.0 Oxide: 1-15m
CRC-548 10 1.0 Oxide: 9-19m
CRC-550 9 1.5 Oxide: 13-22m
CRC-551 5 1.4 Oxide: 3-8m
CRC-554 10 7.8 Oxide: 114-124m
4 3.9 Sulfide: 124-128m
CRC-560 9 1.4 Oxide: 120-129m
CRC-564 9 1.0 Oxide: 11-20m
CRC-567 7 1.0 Oxide: 107-113.5m
CRC-568 8 1.5 Oxide: 84-92m
CRC-572 15 3.0 Sulfide: 25-30m@3.0gpt Au, 56-66m@3.0gpt Au
CRC-573 41 4.1 Oxide: 0-41m, including 21-41m@7.1gpt Au,
27-38m@10.2gpt Au
CRC-575 12 2.6 Oxide: 16-28m
3 3.5 Sulfide: 38-41


A more detailed breakout of drilling results for all 61 drill holes is posted to our website.

Richard C. Moores, President of Anatolia, stated, "We are excited by the discovery of a new gold zone beyond the western limits of the Main Zone, demonstrating the potential for additional ounces. We have also been successful in extending and defining previously known gold mineralization, which should be reflected in future resource updates." Mr. Moores added, "The overall mine development program continues to move forward smoothly with key permits applied for and progressing through the approval process. We are aiming for a 3rd quarter, 2007 completion of the Sulfide Study."

In January 2007, Anatolia made a formal decision to begin development of Copler, focusing on the near surface leachable portion of the deposit. To date, total reserves and resource are 6.3 million ozs gold. Proven and probable reserves are 2.8 million ozs gold. Additional gold resources include measured and indicated oxides of 0.4 million ozs gold, inferred oxides 1.3 million ozs gold, measured and indicated sulfides of 0.7 million ozs gold, and inferred sulfides of 1.1 million ozs gold. Detailed engineering, permitting, equipment procurement, financing and other preconstruction activities are ongoing.

Anatolia currently has 82.6 million common shares issued and outstanding, 98.5 million fully diluted. Anatolia trades on the Toronto Stock Exchange as ANO.

This news release may contain forward-looking statements in respect of various matters including upcoming work programs and events. The results or events predicted in these forward-looking statements may differ materially from actual results or events. Anatolia disclaims any obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise. Assays are performed by OMAC Laboratories, Ireland, and ALS-Chemex, Vancouver, BC, Canada, with quality control of sampling, preparation and assaying overseen by Anatolia, whose President, Richard C. Moores, is a "qualified person" for the purposes of applicable Canadian securities regulations.

Contact Information

  • Anatolia Minerals Development Limited
    Richard C. Moores
    President
    (303) 670-9945
    (303) 670-9947 (FAX)
    or
    Anatolia Minerals Development Limited
    Douglas Tobler
    Chief Financial Officer
    (303) 292-1299
    (303) 297-0538 (FAX)
    Website: www.anatolia-minerals.com