Monument Updates Progress of the Burnakura Gold Project


VANCOUVER, BRITISH COLUMBIA--(Marketwired - Nov. 28, 2016) - Monument Mining Limited (TSX VENTURE:MMY)(FRANKFURT:D7Q1) "Monument" or the "Company" is pleased to announce that it has primarily completed its early stage production implementation plan at the Burnakura Gold Project and moved to a final technical critical flaw review and optimization stage based upon an independent third party's recommendations, targeting completion by the end of December, 2016. The pre-commercial production construction and mine development period is anticipated to be shortened up to three months from six months period due to completion of the offsite work on long lead items in November, 2016 according to the implementation plan. The Burnakura Gold Project is progressed to bring forward cash flow to de-risk its continuing business development in Western Australia.

Progress of Mine Plan and Internal Economic Study

Since the update on the Burnakura Gold Mine development announced in February 2016, the Company has completed the exploration program on North of Alliance ("NOA") 4, 6 and 7/8, and the results have been included in its mine plan in addition to Alliance and New Alliance ("ANA") and Federal City. With the revised mine optimization, high grade ore will be processed through the CIL plant first, low grade ore will be stockpiled and processed through heap leach facilities, planned to be constructed during the second year of the gold commercial production.

The internal economic study including the geological models, mine plans, engineering works and economic analysis has been sent to independent consultants for due diligence review; and additional metallurgical test work and detailed mine delivery schedules for certain deposits are scheduled to complete by December 2016 to mitigate the construction and operation risks, and lift a level of confidence to achieve targeted economic viability. The internal economic assessment shows that the life of mine for early stage production could potentially be extended.

The Company's production decision is not based on a feasibility study of mineral reserves demonstrating economic and technical viability under NI 43-101 standards. Therefore, there is increased uncertainty with economic and technical risks of failure associated with this project, including but not limited to the risk that mineral quantities and grades might be lower than expected, and construction or ongoing mining and milling operations are more difficult or more expensive than expected; production and economic variables may vary considerably, due to the absence of detailed economic and technical analysis prepared in accordance with NI 43-101. There is no guarantee that production will begin as anticipated or at all or that that the production will be able to generate positive cash flow as anticipated in order to return the Company's capital investment.

Progress of Mine Development

The off-site engineering design, refurbishment and procurement work has been completed on long lead items including a three stage crushing circuit of the new primary secondary and tertiary crushers ready for installation at the site in early fiscal 2017, subject to completion of funding arrangements. A site inspection has been completed with Como Engineers and a detailed proposal for the crushing circuit together with a CIL feed plan and a CIL recommissioning plan has been proposed, and a construction schedule has been developed for implementation. This has reduced construction time from six to three months, during which the pre-stripping and mining are planned to stockpile ore for the CIL mill feed.

The stockpile areas have been surveyed and will be established near to the plant for ease of placing material through the heap leach equipment and stacking in due course. All capital heap leach equipment is on site, owned and available for installation when heap leach operations are scheduled to commence.

Other critical movements include completion of a power strategy assessment and building the site power model, waste dump review for submission of mining proposal. Pit dewatering has been assessed for early stage production, access road, ROM pad and crusher feed ramp construction, sorting of store area ready for operational start up have also been completed during the quarter. Plant control laboratory expansion and upgrade and associated works have been completed as well as camp accommodation and kitchen are prepared in readiness for FEED engineers and mining contractors to arrive on site, anticipated to be in January 2017.

The workforce planning has been submitted to management for review and included to the action plan. The key personnel have been located and the key operation management are now on board. The Amended Environmental Protection License for Crushing, Heap Leach and Dewatering was received subsequent to the quarter. In addition all mine planning work for submission of the Mining Proposal was completed.

Deep Drilling Program

Following the encouraging drill results at NOA7-8 (SEDAR filed July 11, 2016) the Company announced that it intends to undertake a deep drilling program to a depth of 500 meters in two stages, first to 250 meters and subject to results, the second stage would be to 500 meters. The program has been reschedule following commencement of early stage mining production.

About Monument

Monument Mining Limited (TSX VENTURE:MMY)(FRANKFURT:D7Q1) is an established Canadian gold producer that owns and operates the Selinsing Gold Mine in Malaysia. Its experienced management team is committed to growth and is advancing several exploration and development projects including the Mengapur Polymetallic Project, in Pahang State of Malaysia, and the Murchison Gold Projects comprising Burnakura, Gabanintha and Tuckanarra in the Murchison area of Western Australia. The Company employs approximately 240 people in both regions and is committed to the highest standards of environmental management, social responsibility, and health and safety for its employees and neighboring communities.

Robert F. Baldock, President and CEO
Monument Mining Limited
Suite 1580 -1100 Melville Street
Vancouver, BC V6E 4A6

FOR FURTHER INFORMATION visit the company web site at www.monumentmining.com.

"Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release."

Forward-Looking Statement

This news release includes statements containing forward-looking information about Monument, its business and future plans ("forward-looking statements"). Forward-looking statements are statements that involve expectations, plans, objectives or future events that are not historical facts and include the Company's plans with respect to its mineral projects and the timing and results of proposed programs and events referred to in this news release. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". The forward-looking statements in this news release are subject to various risks, uncertainties and other factors that could cause actual results or achievements to differ materially from those expressed or implied by the forward-looking statements. These risks and certain other factors include, without limitation: risks related to general business, economic, competitive, geopolitical and social uncertainties; uncertainties regarding the results of current exploration activities; uncertainties in the progress and timing of development activities; foreign operations risks; other risks inherent in the mining industry and other risks described in the management discussion and analysis of the Company and the technical reports on the Company's projects, all of which are available under the profile of the Company on SEDAR at www.sedar.com.

Material factors and assumptions used to develop forward-looking statements in this news release include: expectations regarding the estimated cash cost per ounce of gold production and the estimated cash flows which may be generated from the operations, general economic factors and other factors that may be beyond the control of Monument; assumptions and expectations regarding the results of exploration on the Company's projects; assumptions regarding the future price of gold of other minerals; the timing and amount of estimated future production; the expected timing and results of development and exploration activities; costs of future activities; capital and operating expenditures; success of exploration activities; mining or processing issues; exchange rates; and all of the factors and assumptions described in the management discussion and analysis of the Company and the technical reports on the Company's projects, all of which are available under the profile of the Company on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. The Company does not undertake to update any forward-looking statements, except in accordance with applicable securities laws.

Contact Information:

Monument Mining Limited
Richard Cushing
MMY Vancouver
+1-604-638-1661 x102
rcushing@monumentmining.com
www.monumentmining.com

Wolfgang Seybold
Axino AG-Europe
+49 711-82-09-7211
wolfgang.seybold@axino.de