MONTREAL, QUEBEC--(Marketwire - Aug. 21, 2007) - Temoris Resources (TSX VENTURE:TMO), (shares outstanding and fully diluted:19,068,579 - News; "Temoris").

The Company is pleased to announce the results from the drilling program (665 meters) that took place during the month of June on its Mapimi property in Mexico. The results are very encouraging and exceeding our expectations considering the fact that the program was in its first stage with the first holes ever drilled on the property. Two more showings were identified with the furthest located 1 kilometer away from the actual drilling. An upcoming press release will elaborate on the findings.

Three of the four holes hit mineralization with the third hole being particularly interesting from a geological point of view.

The mineralization was found within a skarn structure with holes #1 and #2 aimed to cut the vertical extension of the first identified surface showing which had yielded the following values:

0.11 g/tAu + 443g/tAg +2.79 % Pb + 9.02%Zn over 3.39m

(See press release March 22, 2007).

Hole #3 cut the eastern extension of the showing where a geochemical and an electromagnetic (max-min) were present.

Hole #4 failed to cut the possible western extension of the showing. There was no prior geochemical or electromagnetic presence.

The results are as follows:



-------------------------------------------------------------------------
Hole # From To Length Au g/t Ag g/t Cu % Zn % Pb %
m m m
-------------------------------------------------------------------------
DDH#1 93 96 3 48 0.28 0.26
-------------------------------------------------------------------------
DDH#2 - - - - - - - -
-------------------------------------------------------------------------
DDH#3 96.1 107 10.9 46.7 0.45 1.66
-------------------------------------------------------------------------
Including 96.1 97.2 1.1 70.5 1.65
-------------------------------------------------------------------------
Including 103.8 105 1.2 240.9 2.08 13.4
-------------------------------------------------------------------------
189.2 193.3 4.1 0.61 27.4 0.80 0.53
-------------------------------------------------------------------------
DDH#4 73.3 74.1 0.8 167 0.37 0.78
-------------------------------------------------------------------------


The company had originally planned to drill 1,500 meters in its phase 1 program and was unable to finish due to the arrival of an early raining season. The remaining 845 meters will be drilled sometime in late September with the end of the raining season. The Company will not need additional funding to complete most of its phase 1.

The technical content of this news release has been approved by Luc Lamarche, a qualified person as defined in National Instrument 43-101.

Forward-Looking Statements

This news release contains certain forward-looking statements. These forward-looking statements are subject to a variety of risks and uncertainties beyond the Company's ability to control or predict which could cause actual events or results to differ materially from those anticipated in such forward-looking statements.

The TSX Venture Exchange does not accept responsibility for the adequacy or accuracy of the release.

Contact Information

  • Temoris Resources Inc.
    Jean Labrecque
    President & CEO
    514-866-6001 Ext. 229
    514-866-6193
    www.tmoris.com